MemotivaPMP Exam Flashcards: Earned Value Management, CPI, SPI, EVM Formulas

What does a negative Schedule Variance indicate?

Nortren·

What does a negative Schedule Variance indicate?

0:30

Schedule Variance, or SV, equals Earned Value minus Planned Value. A negative SV means the project has completed less work than planned at this point in time, indicating the project is behind schedule. A positive SV means more work has been completed than planned, indicating the project is ahead of schedule. An SV of zero means the project is exactly on schedule. For example, if PV is 50,000 dollars and EV is 40,000 dollars, SV is negative 10,000 dollars, meaning the project is behind by 10,000 dollars worth of scheduled work.
pmi.org