What is the critical path method and why does it matter?

Nortren·

What is the critical path method and why does it matter?

0:30

The critical path method identifies the longest sequence of dependent activities that determines the minimum project duration. Any delay on a critical path activity directly delays the project completion date because these activities have zero float or slack. Non-critical activities have float, meaning they can be delayed without affecting the project end date. To find the critical path, perform a forward pass calculating early start and early finish dates, then a backward pass calculating late start and late finish dates. The difference between early and late dates is the float.
pmi.org